Praxis Report Rules out Suitibility of Lower Shannon
Estuary This report has shown that the harsh wave
climate renders this location unsuitable for an
offshore windfarm.
DECEMBER
2006
Tradewinds
signs 51 megawatt contract UNDER government-sponsored
Renewable Energy Feed-In TARIFF (REFIT). This
contract is for a fifteen year period and is 100%
index linked to the Consumer Price Index (CPI).
Tradewinds
accepts additional grid connection offer for 18
megawatt at Athea.
Tradewinds signs grid connection
agreement with Eirgrid.
JANUARY
2007
Athea
site facility now extended to 120 megawatts. This
will increase the total amount of windmills at this
site to 40.